Equipment shortages add pressure to LNG plant costs, Kiewit says



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>Equipment shortages add pressure to LNG plant costs, Kiewit says</title></head><body>

New LNG plant construction costs up to 30% in five years

Higher costs reflected in tariffs charged new customers

Wages up 20%

By Curtis Williams

HOUSTON, Sept 19 (Reuters) -The boom in U.S. construction of liquefied natural gas (LNG) plants has led to shortages of generators, electric motors and transformers, contributing to higher costs and construction delays, Kiewit Energy President Tom Shelby said on Thursday.

Equipment shortages and rising costs for equipment, wages and cement have driven up the cost of constructing new LNG plants by between 25% and 30% over the last five years, Shelby said, noting that wages have increased by 20% in keeping with inflationary costs.

Kiewit, among the largest U.S. contractors, has been involved in building LNG plants including Venture Global's 12 million tons per annum (MTPA) plant at Calcasieu Pass, Louisiana.

"For most of my career transformers from order to supply took one year. Now, it's up to nearly two years," Shelby told Reuters on the sidelines of the Gastech conference in Houston.

Separately, energy researcher Wood Mackenzie said fees LNG developers charge new customers to liquefy gas have been climbing.

Twenty-year gas processing deals signed in 2022 and early 2023 were priced between $2.15 per million British thermal units and $2.30/mmBtu. More recent deals have put tariffs in the $2.40/ mmBtu to $2.50/mmBtu range, Wood Mackenzie said.

Equipment availability can no longer be taken for granted, and shortages have been compromising quality.

"It affects us as an EPC (engineering, procurement and construction) contractor in terms of the quality and the time," said Shelby.

There are five LNG plants under development in Texas and Louisiana and 16 others on the drawing board looking to secure investment and customers. The five under construction would add a combined 86.6 million metric tons per annum (MTPA) of the superchilled gas.

Work at Golden Pass LNG, one of the largest U.S. projects, largely halted after its main contractor ran $2.4 billion over the original budget and filed for bankruptcy earlier this year. The project's joint owners, QatarEnergy QATPE.UL and Exxon Mobil XOM.N, recently asked for a three year extension to their construction permit.



Reporting by Curtis Williams in Houston; Editing by David Gregorio

</body></html>

免责声明: XM Group仅提供在线交易平台的执行服务和访问权限,并允许个人查看和/或使用网站或网站所提供的内容,但无意进行任何更改或扩展,也不会更改或扩展其服务和访问权限。所有访问和使用权限,将受下列条款与条例约束:(i) 条款与条例;(ii) 风险提示;以及(iii) 完整免责声明。请注意,网站所提供的所有讯息,仅限一般资讯用途。此外,XM所有在线交易平台的内容并不构成,也不能被用于任何未经授权的金融市场交易邀约和/或邀请。金融市场交易对于您的投资资本含有重大风险。

所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。

本网站上由XM和第三方供应商所提供的所有内容,包括意见、新闻、研究、分析、价格、其他资讯和第三方网站链接,皆保持不变,并作为一般市场评论所提供,而非投资性建议。所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为适用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。请确保您已阅读并完全理解,XM非独立投资研究提示和风险提示相关资讯,更多详情请点击 这里

风险提示: 您的资金存在风险。杠杆商品并不适合所有客户。请详细阅读我们的风险声明