GE Vernova blames latest offshore wind blade failure on high winds, shares rise



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-GE Vernova blames latest offshore wind blade failure on high winds, shares rise</title></head><body>

GE Vernova reports unrelated turbine blade failures

Latest blade accident blamed on strong winds during storm

Three blade accidents in 4 months raise concerns for GE Vernova

Adds details on storm damage, analyst comment, share activity throughout; adds bullet headlines

Aug 30 (Reuters) -Energy equipment maker GE Vernova GEV.N on Friday said recent turbine blade failures at two offshore wind farms in the United States and the United Kingdom are unrelated and blamed the latest mishap on strong winds.

The statement comes as the company has been grappling with fallout from three separate blade accidents in four months at two wind farms that are still under construction. GE Vernova shares were up 3% following the announcement.

The most recent occurred on Aug. 22 at the Dogger Bank wind farm off the coast of Yorkshire in the North Sea, a little over a month after a blade fell apart at the Vineyard Wind project off the coast of Massachusetts and sent debris onto nearby beaches. A blade at Dogger Bank was also damaged in May during installation.

The Vineyard Wind blade damage was blamed on a manufacturing flaw, raising concerns about a more widespread issue.

The failure this month occurred when the turbine rotor was locked in place and the yaw system, which orients the rotor towards the wind, was disabled, the company said, leaving it vulnerable during a large storm. The turbine was in the process of being commissioned.

GE Vernova said it was taking corrective actions to eliminate risks during such events.

"We continue to investigate the recent offshore wind events involving our blades and are taking every necessary step with customers and authorities to safely move forward with the installation of the Dogger Bank and Vineyard Wind farms," GE Vernova said in a statement. "Our current analyses indicate that the causes of the recent blade events are unrelated."

Two analysts, Chris Dendrinos of RBC Capital Markets and Graham Price of Raymond James, said the news was positive for GE Vernova because it did not point to a broader manufacturing problem.

"It is unfortunate especially given the concerns and tensions stemming from the blade failure at Vineyard, but this appears to be an isolated event and a risk the company has to deal with due to unpredictable operating conditions in the North Sea," Dendrinos said in an email.

Dogger Bank is a partnership between Britain's SSE Renewables and Norwegian companies Equinor EQNR.OL and Vargronn.

Vineyard Wind is a joint venture between Avangrid AGR.N, the U.S. arm of Spain's Iberdrola IBE.MC, and Denmark's Copenhagen Infrastructure Partners.

GE Vernova shares were up $5.66, or 3%, at $197.02 in afternoon trading on the New York Stock Exchange.



Reporting by Nichola Groom; Editing by Kirsten Donovan and Jonathan Oatis

</body></html>

免责声明: XM Group仅提供在线交易平台的执行服务和访问权限,并允许个人查看和/或使用网站或网站所提供的内容,但无意进行任何更改或扩展,也不会更改或扩展其服务和访问权限。所有访问和使用权限,将受下列条款与条例约束:(i) 条款与条例;(ii) 风险提示;以及(iii) 完整免责声明。请注意,网站所提供的所有讯息,仅限一般资讯用途。此外,XM所有在线交易平台的内容并不构成,也不能被用于任何未经授权的金融市场交易邀约和/或邀请。金融市场交易对于您的投资资本含有重大风险。

所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。

本网站上由XM和第三方供应商所提供的所有内容,包括意见、新闻、研究、分析、价格、其他资讯和第三方网站链接,皆保持不变,并作为一般市场评论所提供,而非投资性建议。所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为适用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。请确保您已阅读并完全理解,XM非独立投资研究提示和风险提示相关资讯,更多详情请点击 这里

风险提示: 您的资金存在风险。杠杆商品并不适合所有客户。请详细阅读我们的风险声明