Global plan for early ditch of coal power hits Indonesia hurdle



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>Global plan for early ditch of coal power hits Indonesia hurdle</title></head><body>

July deadline to agree Cirebon-1 power price deal lapsed

Jakarta concerned about finance and legal risks

ADB says private sector banks lined up to back a deal

By Gayatri Suroyo and Fransiska Nangoy

CIREBON, Indonesia, Sept 25 (Reuters) -A G7-backed push to close coal power plants in emerging markets is facing further delays after a July deadline passed without a deal on the early closure of an Indonesian power plant that would be the first to shut under the initiative.

The push against coal comes under the Just Energy Transition Partnerships (JETPs) with Indonesia, Senegal,South Africa and Vietnam that call for billions of dollars in investments, grants and loans from G7 members, multilateral banks and private lenders to help them transition to low-carbon economies.

Cutting emissions from coal, the dirtiest fossil fuel, is seen as a crucial element of the JETPs if the world is to stave off the worst impacts of climate change.

But a deal on the early shutdown of coal power plants in South Africa remains elusive amid its struggles with rolling blackouts, and hope for proof of concept has turned to Indonesia's 660 megawatt Cirebon-1 plant in West Java province, 220 km (140 miles) east of capital Jakarta.

The legal and financial implications of closing Cirebon-1 are a stumbling block though. Jakarta is worried, too, that costs for replacing it with renewable energy could reach $1.3 billion, mostly in subsidies to cover more expensive renewable power generation, according to the finance ministry.

A new government is taking office in October as well and that could further dent the chance of a deal on Cirebon, said Fabby Tumiwa, a renewables expert and member of the technical team advising Indonesia on its JETP.

"If this is not signed before Oct. 20, I am worried that this matter will be overlooked," Fabby said, citing calls by President-elect Prabowo Subianto for self-sufficiency and energy security that suggest a commitment to coal, which generates two-thirds of Indonesia's electricity.

Prabowo, who takes office on that date, has not commented on Cirebon and has rarely discussed his energy policy, though the retirement of coal power is mentioned in his campaign pledges.

Prabowo's team has not responded to requests for comment.

Under Indonesia's JETP, richer nations have pledged $20 billion to help the Southeast Asian nation with its energy transition, although little of that money has been disbursed.

LEGAL CONCERNS

Earlier this month, Finance Minister Sri Mulyani Indrawati said the outgoing government was trying to close the Cirebon deal as soon as possible, without giving details.

David Elzinga, team leader for the Asian Development Bank's regional Energy Transition Mechanism programme that is working on the early shutdown scheme, said his group was seeking a binding deal on Cirebon acceptable to both the outgoing and incoming administrations.

"Indonesia has positioned itself to be a leader ... It's really important now that we get the deal done," Elzinga said.

A deal on Cirebon is crucial for the ADB's regional ETM programme as it plans similar deals in countries including Vietnam and the Philippines, as well as for other plants in Indonesia.

To get there, state utility Perusahaan Listrik Negara (PLN) and plant operator PT Cirebon Electric Power (CEP) need to reach a new power purchase agreement, which they failed to do by July, CEP Director Joseph Pangalila told Reuters.

The need for stronger legal protections and a clear road map for retiring coal plants was the main problem, PLN said, given that power generation costs could rise by nearly 90%.

PLN directors also fear a deal could expose them to future criminal charges if anti-graft investigators see the transaction as burdening the state with losses, JETP advisor Fabby said.

Rachmat Kaimuddin, deputy minister overseeing power infrastructure, acknowledged this at a recent forum, saying stakeholders were considering the legal repercussions that might arise from any closures.

"If we're not careful, some people can get into trouble because it can create what they call state loss," he said.

In June, a former chief executive of state energy firm Pertamina was sentenced to nine years in jail for signing a long-term gas contract that a corruption court said caused state losses of $114 million.


OTHERS TO FOLLOW

"We are anxious that it needs to get done, but at the same time what is important is that the first transaction be done in the best possible manner," said Ramesh Subramaniam, ADB director general and head of the bank's sectors group.

A number of private banks are lined up to invest and a series of new deals could also be kicked off once Cirebon is done, with the ADB having already looked at about 30 other plants in Indonesia, he said.

"Although this has taken time, we have learnt a lot ... and our very clear feeling is the next ones to come will be considerably easier."

Cirebon-1 is a fairly new plant that started up in 2012. A deal would mean it stops operations in 2035 instead of 2042.

Despite running cleaner than older plants, emissions from Cirebon and others around Jakarta are often blamed for Indonesia's chronic pollution, and some of the locals in neighbouring fishing villages would be happy to see it go.

Fisherman Amin, 64, blamed the plant and coal unloading at its jetty for pollution and a scarcity of fish in nearby waters.

"When they first opened, the water was fine, but it became increasingly murky. The green mussel farms here didn't have any harvest in the past two years," he said.

"From the beginning of construction, I was against it."


($1 = 15,475 rupiah)


Indonesia PLN's electricity production by power sources https://reut.rs/3XOfCuz

World's top 10 green house gas emitters in 2023 https://reut.rs/3zo7K9S

FACTBOX-Global JETP plans to clean up developing nations' power sectors nL4N3L20WF


Reporting by Gayatri Suroyo and Fransiska Nangoy; Additional reporting by Bernadette Christina Munthe and Stefanno Sulaiman in Jakarta and Simon Jessop in London; Editing by Tom Hogue

</body></html>

免责声明: XM Group仅提供在线交易平台的执行服务和访问权限,并允许个人查看和/或使用网站或网站所提供的内容,但无意进行任何更改或扩展,也不会更改或扩展其服务和访问权限。所有访问和使用权限,将受下列条款与条例约束:(i) 条款与条例;(ii) 风险提示;以及(iii) 完整免责声明。请注意,网站所提供的所有讯息,仅限一般资讯用途。此外,XM所有在线交易平台的内容并不构成,也不能被用于任何未经授权的金融市场交易邀约和/或邀请。金融市场交易对于您的投资资本含有重大风险。

所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。

本网站上由XM和第三方供应商所提供的所有内容,包括意见、新闻、研究、分析、价格、其他资讯和第三方网站链接,皆保持不变,并作为一般市场评论所提供,而非投资性建议。所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为适用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。请确保您已阅读并完全理解,XM非独立投资研究提示和风险提示相关资讯,更多详情请点击 这里

风险提示: 您的资金存在风险。杠杆商品并不适合所有客户。请详细阅读我们的风险声明